The report date is the date of the costs in the report. To get costs for a different date, enter the report data for the cost data you want to use (in the format of mm/yyyy).
The earliest date available is October 1975, and the latest date is the current month and year.
Example: To calculate the costs as of March, 1997, enter 3/1997 in this field.
Note: When you enter a Report Date, all costs in the report will be as of this date. To have all the costs in the report be as of one date, and also have an additional line in the report with the total cost indexed to a different date, use the Single Line Backdate field on this screen.